Major Biomass and Industrial Development Refused as CPRENEY Object

27th May 2025

CPRE North and East Yorkshire (CPRENEY) welcomes the decision by East Riding of Yorkshire Council to refuse planning permission for a large-scale industrial development proposed by GB-Bio Limited at Hull Road, Aldbrough.

The planning application (Ref: 21/04544/STPLFE) sought both full and outline permission for a major hybrid development, including a biomass and waste wood processing plant, vertical farming units, carbon dioxide storage tanks, substations, and extensive infrastructure across open countryside.

In a comprehensive refusal issued under the Town and Country Planning Act 1990, the Council rejected the application due to the unjustified scale and harmful visual and cumulative impacts on the local landscape.

The proposal was described as an attempt to develop a bio-production park next to an existing but non-operational biomass facility, without sufficient evidence to justify its scale or its need. The Council found the development would industrialise open farmland, creating a detrimental effect on the intrinsic countryside character, despite proposed screening and landscaping.

The refusal also highlighted key policy conflicts, stating the proposal was contrary to the East Riding Local Plan Strategy Document policies EC1, S4, EC5, and ENV1, as well as failing to meet the requirements of paragraph 160 of the National Planning Policy Framework (NPPF). These policies stress that development in the open countryside must be of appropriate scale, adjacent to existing industrial areas, and must protect rural character and landscape.

In his signed decision, Stephen Hunt MRTPI, Director of Planning and Development Management, confirmed that while the low-carbon energy benefits were considered, they did not outweigh the significant and unjustified harm to the countryside.

This refusal represents a strong statement in support of planning integrity, policy-based decision-making, and the protection of rural landscapes.

Key reasons for refusal included:

  • No clear justification for the scale of development in relation to the existing facility.
  • Unacceptable visual impact from roads and footpaths, harming the open countryside.
  • Conflict with policies requiring developments to respect rural character and be appropriately scaled.
  • The public benefits of renewable energy did not outweigh the environmental harm.

 

CPRENEY commends this outcome, which reaffirms the need to carefully balance renewable energy ambitions with the preservation of our countryside’s character and beauty.

CPRENEY Statement:

“This is a huge win for East Yorkshire’s countryside. The proposed development was wholly inappropriate for this location – vast in scale, poorly justified, and visually damaging. We are proud to have worked with local residents to ensure this beautiful landscape remains protected for future generations.”

To see the whole application follow this link – 21/04544/STPLFE | Hybrid Application consisting of: a) Full Planning Permission for the erection of a biomass and waste wood processing building with curtilage hardstanding, creation of an open storage area with stockpiling pens/bays, erection of fire pump house and installation of a weighbridge, construction of access and service road with associated parking and creation of reed bed and rainwater harvesting lagoons, planting of a woodland block and associated landscaping and boundary treatments and enclosures and b) Outline Planning Permission for the erection of up to 4 vertical farming units, creation of up to 2 rainwater harvesting lagoons and 1 attenuation pond with associated works (Northern Development Parcel), construction of up to 6 carbon dioxide storage tanks, underground and overground pipelines and electrical power cabling, construction of a 11kV substation and a high voltage substation with associated landscaping, hedgerows, fencing and wildlife habitats (All Matters Reserved) (SUBMISSION OF AMENDED SCHEME) | GB Bio Limited Hull Road Aldbrough East Riding Of Yorkshire HU11 4RE

To see our objection follow this link – ERY – Aldbrough Hydrogen Storage Project – North and East Yorkshire