North Yorkshire Council – ZB25/00821/FUL- Raskelf Solar Farm
Authority: North Yorkshire Council (Hambleton)
Type of consultation: Planning Consultation
Full details of application/consultation: ZB25/00821/FUL – Construction and operation of up to a 30MW Solar PV farm, comprising ground-mounted Solar PV Arrays, 132kV DNO substation, customer substation, spares container, new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, landscaping, temporary construction compound and all ancillary grid infrastructure and associated works.
At land: Boscar Layby, Land North East Of Raskelf, North Yorkshire
Type of response: Objection
Date of Submission: 7th August 2025
North Yorkshire Council - ZB25/00821/FUL- Raskelf Solar Farm
PDF 361.76 Kb